1
/
of
1
Built Intelligence
NEC3 ECC Programme Submission Template
NEC3 ECC Programme Submission Template
Couldn't load pickup availability
Use this free downloadable template to help you create a programme submission under the NEC3 Engineering and Construction Contract (ECC).
The ECC considers the programme to be a management tool of vital importance requiring the Contractor to make regular programme submissions, requiring the programme to comply with the contract and requiring the Project Manager to accept or not accept. When it is accepted, it becomes the latest Accepted Programme. Sanctions exist against the Contractor if a programme is not submitted when it should be or if no Accepted Programme is in place.
You can use this NEC3 ECC template for the Contractor’s submission and the Project Manager’s reply as follows:
- Submit under clause 31.1 a programme
- Submit under clause 32.1 a revised programme
- Reply under clause 31.1 or 32.2 to a programme submission
- Instruct under 32.2 to submit a revised programme