1
/
of
1
Built Intelligence
NEC3 ECS Subcontractor Quotation for Compensation Event (CEQ) Template
NEC3 ECS Subcontractor Quotation for Compensation Event (CEQ) Template
Couldn't load pickup availability
Use this free downloadable template to help you put together a Subcontractor quotation for a compensation event under the NEC3 Engineer and Construction Subcontract (ECS).
After giving the instruction and notifying the compensation event, the Contractor is required to instruct the Subcontractor to submit quotations, unless the event arises from a fault of the Subcontractor or quotations have already been submitted. This is stated in clause 61.1.
The quotation as a minimum must set out the cost effect on total of the Prices and the time effect on the Completion Date, Key Date(s) and Sectional Completion Date(s)
You can download this template as a PDF for free!