NEC4 ECS Compensation Events (CE) Template
NEC4 ECS Compensation Events (CE) Template
Use this free downloadable template to help you create a compensation event notification under the NEC4 Engineering and Construction Subcontract (ECS).
Compensation events are events listed in the contract which, if they occur and do not arise from the Subcontractor’s fault, entitle the Subcontractor to be compensated for any effect the event may have on Prices, the Completion Date and any Key Dates.
The ECS contains strict notification and procedural requirements which take a compensation event from notification to implementation.
You can use these NEC4 ECS templates for notifying the following compensation events:
- Notify under clause 60.1(1) of an instruction to change the Subcontract Scope
- Notify under clause 60.1(2) that the Contractor does not allow access to the Site
- Notify under clause 60.1(3) that the Contractor does not provide something that it is to provide
- Notify under clause 60.1(4) of an instruction to stop or not start work or to change a Key Date
- Notify under clause 60.1(5) that the Contractor, Client or Others do not work within the stated constraints
- Notify under clause 60.1(6) that the Contractor does not reply to a communication
- Notify under clause 60.1(7) of an instruction dealing with an object of interest or value
- Notify under clause 60.1(8) that the Contractor has changed a decision
- Notify under clause 60.1(9) that the Contractor withholds an acceptance
- Notify under clause 60.1(10) of an instruction to search for a Defect and no Defect is found
- Notify under clause 60.1(11) that a test or inspection causes unnecessary delay
- Notify under clause 60.1(12) that the Subcontractor encounters unexpected physical conditions
- Notify under clause 60.1(13) that an extreme weather measurement is recorded
- Notify under clause 60.1(14) of an event which is the Contractor’s or Client's liability
- Notify under clause 60.1(15) that the Contractor certifies take over before Completion
- Notify under clause 60.1(16) that the Contractor does not provide materials for testing
- Notify under clause 60.1(17) that the Contractor notifies a correction to an assumption
- Notify under clause 60.1(18) of a breach by the Contractor
- Notify under clause 60.1(19) of a prevention event
- Notify under clause 60.1(20) that a quotation for a proposed instruction is not accepted
- Notify under clause 60.4 of a difference between the final total quantity of an item and the quantity in the Bill of Quantities which delays completion (main Options B and D)
- Notify under clause 60.5 of a difference between the final total quantity of an item and the quantity in the Bill of Quantities (main Options B and D)
- Notify under clause 60.6 of the correction of a mistake in the Bill of Quantities caused by a departure from the method of measurement (mail Options B and D)
- Notify under clause X2.1 of a change in the law
- Notify under clause X12.3(6) of a change in the Partnering Information
- Notify under clause X12.3(7) of a change in the Partnering Timetable
- Notify under clause X14.2 of a delay in making advanced payment
- Notify under clause X15.2 of correcting a Defect for which the Contractor is not liable
- Notify under clause Y2.5 of suspension of performance
You can also use these templates to:
- Instruct the Subcontractor under clause 60.6 to correct a mistake in the Bill of Quantities (main Options B and D)
- Instruct the Subcontractor under clause 61.2 and 61.4 to submit a quotation for a compensation event
- Reply under clause 61.4 to the Subcontractor’s notification of a compensation event
- Notify under clause 61.4 and 62.5 of an agreement to extend the period for a submission or reply
- Notify under clause 61.4, 62.6 and 64.4 of a failure of the Contractor to respond or make an assessment
- Notify under clause 61.5 that the Contractor has decided that the Subcontractor did not give early warning
- Notify under clause 61.6 of a correction because an assumption on which a compensation event is based was wrong
- State assumptions under clause 61.6 about the event
- Instruct the Subcontractor under clause 62.1 to submit alternative quotations for a compensation event
- Reply to a quotation under clause 62.3
- Submit a quotation for a compensation event under clause 62.3
- Notify under clause 64.3 of the Contractor’s assessment of a compensation event
- Instruct the Subcontractor under clause 65.1 to submit quotations for proposed instructions
- Submit a quotation for a proposed instruction under clause 65.2
- Notify under clause 65.2 of a reply to a quotation for a proposed instruction